PROJECT DELIVERY ANALYSIS PROJECTS

Meadow Lake OSB Plant for Tolko Industries Ltd., Vernon BC

Description of Project
Development of a $200 million greenfield OSB (Oriented Strand Board) plant at Meadow Lake, Saskatchewan.


Description of Services

Bramcon worked with the staff of Tolko Industries Ltd. to plan and execute the Definition Phase (process development, site selection, and environmental approval) for a plant designed to produce 600 million square feet per year of 3/8 inch panels. Scope included project delivery analysis and organization analysis. Phase culminated with the issue of a comprehensive Project Definition Report. The project proceeded to construction and started up in August 2003.

Greenfield OSB Plant for Tolko Industries Ltd., Vernon BC

Description of Project
Development phase of a greenfield OSB plant at Kenora, Ontario.

Description of Services
Bramcon worked with Tolko Industries Ltd. to undertake a project delivery and organization analysis for the Kenora OSB by surveying the previous four plants' projects for organization structure and project performance. This project did not proceed to construction.

Sawmill Rebuild Project for Tolko Industries Ltd., Vernon BC

Description of Project
Development phase of a $70 million sawmill rebuild at The Pas, Manitoba.

Description of Services
Bramcon worked with Tolko Industries Ltd. to undertake a project delivery and organization analysis for The Pas sawmill rebuild. This sawmill rebuild project was successfully completed in 2000.

Northwest Light Rail Transit Extension for the City of Calgary

Description of Project
Extension of a divided freeway with Light Rail Transit (LRT) in the median for the City of Calgary, Alberta.

Description of Services
Bramcon undertook a project delivery analysis which recommended a design/build delivery over the traditional design/bid/build delivery. The project was successfully constructed by design/build in 2000.

John Hart Bridge and Interchange for the BC Ministry of Transportation, Prince George BC

Description of Project Construction of a new highway bridge over the Nechako River complete with interchange.

Description of Services
Following the completion of the Value Analysis Study, Bramcon undertook a project delivery analysis which recommended a design/build delivery over the traditional design/bid/build delivery. The project was successfully constructed by design/build in 2000.

 

Roberts Bank Rail Corridor 232nd Street Overpass, Langley, BC

Description of Project
Two-line overpass taking an arterial road over CP rail tracks.

Description of Services
Bramcon undertook a project delivery analysis which recommended a design/build delivery and utilized the Early Contractor Involvement method of selecting the design/build contractor.